Garney Construction is the General Contractor for the East Bank Regional Sanitary Sewer Lift Station in Nashville, TN. This project is a Progressive Design-Build, and Garney has partnered with SSR as the Design Engineer. The project owner is Tennessee Stadium, LLC (Titans) with the end user being Metro Water Services (MWS). View flyer.

Garney will be submitting pricing to the Owner for the second Construction Phase (”GMP2”) in mid-to- late January 2025. The GMP2 Design Documents, and associated bid packages, will be available to any interested vendors/subcontractors no later than December 13th, 2024. These bids will be due to Garney by mid-January 2025. GMP2 contracts will be awarded immediately following Owner approval of Garney’s GMP2 pricing, approximately early February 2025. (Exact dates will be discussed further during the Outreach Meeting and in the Bid Packages).

Garney is looking to receive bids based off the GMP2 Design Documents for the following scopes:

  • Division 02 – micropiles, supply aggregates

  • Division 03 – furnish resteel, tie resteel

  • Division 07 – dampproofing & waterproofing subcontractor

  • Division 11 – supply dry pit submersible pumps, VFDs, slide gates, odor control system

  • Division 15 – furnish electric actuated valves, manual process valves

  • Division 16 – electrical subcontractor, furnish & install generator

Garney will be submitting pricing to the Owner for the final Construction Phase (”GMP3”) in mid-to-late March 2025. The GMP3 Design Documents, and associated bid packages, will be available to any interested vendors/subcontractors by mid-February 2025. These bids will be due to Garney by mid-March 2025. GMP3 contracts will be awarded immediately following Owner approval of Garney’s GMP3 pricing, approximately late March 2025. (Exact dates will be discussed further during the Outreach Meeting and in the Bid Packages).

Garney is looking to receive bids based off the GMP3 Design Documents for the following scopes:

  • Division 02 – final asphalt/paving, final site fencing

  • Division 04 – masonry subcontractor

  • Division 05 – supply miscellaneous metals, furnish & install steel trusses, furnish & install steel bar joists

  • Division 07 – furnish & install metal deck roofing, joint sealants

  • Division 08 – furnish & install metal doors and frames, furnish & install motorized overhead doors

  • Division 09 – epoxy coatings & equipment/pipe painting subcontractor

  • Division 10 – supply building signage

  • Division 14 – furnish & install bridge crane

  • Division 15 – furnish & install odor control duct, interior ductile iron pipe, stainless-steel pipe supports,

  • HVAC subcontractor, furnish & install louvers and fire protection

  • Division 17 – instrumentation and controls (includes magnetic flowmeter & system integration)

The project has a 25% DEI participation goal (13% MBE, 12% WBE).